Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Gold_12th on Sun Jan 4 15:31:45 2015

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Bids open around March 2015.
Project cost: OVER $50 million

The Canarsie Tunnel consists of 2 tracks (Q1/Q2) of the “L” subway line between First Ave Station in Manhattan and Bedford Ave Station in Brooklyn.

Super storm Sandy struck New York City on October 29, 2012 and severely flooded the Canarsie Tunnel, especially between the Avenue D Fan Plant/Shaft and North 7th Fan Plant/Shaft.

This project is for the repair and rehabilitation of the Canarsie Tunnel including...
1. Demolition and reconstruction of concrete duct banks

2. Removal and replacement of power and communication cables and equipment

3. Constructions of 2 new underground Circuit Breaker Houses (CBH61 and 62)

4. Replacement of damaged rails and contact rails; reconstruction of damaged mid river pump room and discharge pipes

5. Replacement of damaged signal cables and equipment; and replacement of tunnel lighting cables and fixtures.



The key elements of work are described as follows:
1. Duct banks: Demolition and reconstruction of the inner and outer duct banks from 1st Avenue Station in Manhattan to Bedford Avenue Station in Brooklyn for approximately 30,330 linear feet. Demolition of upper wall ducts (inner wall) between Avenue D shaft in Manhattan and North 7th Shaft in Brooklyn for a total of 6,872 feet.

2. Power System: Removal and replacement of various power cables throughout the tunnel, including negative feeder cables, positive cables, battery cables, control cables, and Tunnel shell protection cables.

3. Communication Systems: Removal and replacement of various communications cables throughout the Tunnel such as 36-strand Fiber Optic Cables (about 50,000 LF), various sizes of Copper Cables (about total: 41,350 LF) and Radio/Antenna Cables (15/8” Radiating Cable and 7/8” Non-Radiating Cable – 38,000 LF) on the walls and/or in the duct banks of the Tunnel. Work also includes removal and installation of 40 Emergency Alarm/ Emergency Telephone units to be provided by NYCT and removal and replacement of FDNY sound powered telephone cables and jacks.

4. Circuit Breaker House (CBH) #61 and #62: Removal of existing Circuit Breaker House #61, currently located mid-river in the Canarsie Tunnel, and construction of new CBH #61 at the location adjacent to Emergency Exit 171 below East 14th Street near Ave B in Manhattan. Removal of existing CBH#62 and construction of new CBH#62 at the location adjacent to north end platform of Bedford Avenue Station. For these two CBHS, remove and install positive, battery and control cables; copper buses; control terminal box, RAIC; relay panels, battery switch box, lighting fixtures, heaters, switches and cables; install flood doors.

5. Track: Replace about 5,000 LF of rails between Avenue D and North 7th Vent Shaft (2500 LF on each Track Q1 and Q2. 6. Pump Room # 1035: Complete reconstruction of pump room #1035, including installation of new discharge line between Avenue D shaft in Manhattan and North 7th Shaft in Brooklyn for a total of 6,872 feet

Duration of Contract 40 Months
Probably weekend shutdown due to date of the contract, 3+ years.

Post a New Response

(1331889)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by SLRT on Sun Jan 4 16:36:04 2015, in response to Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Gold_12th on Sun Jan 4 15:31:45 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Look for a boom in M Line service.

Post a New Response

(1331903)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by AlM on Sun Jan 4 17:30:28 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by SLRT on Sun Jan 4 16:36:04 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
They should definitely extend the M past Essex when that happens.


Post a New Response

(Sponsored)

iPhone 6 (4.7 Inch) Premium PU Leather Wallet Case - Red w/ Floral Interior - by Notch-It

(1331935)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by localacrosstheplatform on Sun Jan 4 19:11:48 2015, in response to Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Gold_12th on Sun Jan 4 15:31:45 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
And, lo, there will be much wailing and gnashing of teeth from the Williamsburg hipsters.

Post a New Response

(1331936)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by italianstallion on Sun Jan 4 19:17:17 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by localacrosstheplatform on Sun Jan 4 19:11:48 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
And it's appropriate, just as it was when the 7-line users, hardly hipsters, wailed about weekend service cuts.

Post a New Response

(1331954)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Nilet on Sun Jan 4 20:12:18 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by AlM on Sun Jan 4 17:30:28 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
They usually extend the M to 57th/6th when the L goes down.

Post a New Response

(1331995)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by italianstallion on Mon Jan 5 00:24:24 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Nilet on Sun Jan 4 20:12:18 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Aha! They CAN turns trains at 57th!

Post a New Response

(1332006)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Nilet on Mon Jan 5 00:47:36 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by italianstallion on Mon Jan 5 00:24:24 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Yeah. They turn M trains there on weekends when the L is down, they turn Q trains there at night when the BMT is closed for Fast Track and they turned B and Q trains there in 1998 when the line between there and Lexington Avenue was closed for some reason.

...and they turned B, F, KK, JFK, and various other trains there when it was a terminal station prior to 1989.

Post a New Response

(1332035)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Wallyhorse on Mon Jan 5 06:47:17 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Nilet on Mon Jan 5 00:47:36 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
I would this time myself extend the (M) and have it go to 145th/St. Nicholas (via the (B) after 47th-50th) since the MTA to use that as an experiment to see if on a more permanent basis having a 6th Avenue-CPW local is worth it.

Post a New Response

(1332038)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Stef on Mon Jan 5 07:17:44 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Wallyhorse on Mon Jan 5 06:47:17 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
For that, they may as well run the B on the weekend.

-Stef

Post a New Response

(1332041)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by MainR3664 on Mon Jan 5 07:51:53 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by localacrosstheplatform on Sun Jan 4 19:11:48 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Well, it's no doubt inconvenient, and I sympathize. But the line has to be repaired...

Post a New Response

(1332071)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Allan on Mon Jan 5 11:32:35 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by italianstallion on Mon Jan 5 00:24:24 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Yes, but it is a very QUICK turn so they do not block F train service.

Post a New Response

(1332179)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Gold_12th on Tue Jan 6 01:43:21 2015, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Nilet on Sun Jan 4 20:12:18 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
Or even better, Forest Hills-71 Av.

Post a New Response

(1381168)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by gOld_12th on Thu Jan 14 00:53:37 2016, in response to Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Gold_12th on Sun Jan 4 15:31:45 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
one year later, lol.

Post a New Response

(1381178)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Wallyhorse on Thu Jan 14 07:35:38 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Nilet on Sun Jan 4 20:12:18 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
For this type of a shutdown, I would seriously consider having the (M) go to 145th Street-8th Avenue OR (once the SAS opens) 96th/2nd on weekends UNLESS the (M) can run its regular weekday route on weekends while Queens Boulevard work goes on.

57th/6th is not ideal for a long-term terminal (even on weekends) due to the (F) using that as a through station.


Post a New Response

(1381191)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by #5 - Dyre Ave on Thu Jan 14 10:44:38 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Allan on Mon Jan 5 11:32:35 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
And it's only been done occasionally. If the MTA is ok with turning M trains at 57/6 every weekend while the Canarsie tubes are being repaired, then that's probably the best option.

Post a New Response

(1381234)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by caine515 on Thu Jan 14 14:56:39 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by #5 - Dyre Ave on Thu Jan 14 10:44:38 2016.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
they can do that regulary...once the 53rd Street tubes are done..cause right now weekend "E" are going through 63rd Street.

Post a New Response

(1381238)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Allan on Thu Jan 14 15:21:11 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by gOld_12th on Thu Jan 14 00:53:37 2016.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
You think anyone will notice?






Post a New Response

(1381284)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by randyo on Thu Jan 14 18:39:26 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Wallyhorse on Thu Jan 14 07:35:38 2016.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
There was a time when the NYCTA limited the number and location of GOs that could be operated at any one time, but unfortunately that is no longer the case so it’s hard to predict what would be the most appropriate routing for a long term extension of the M when the N 7 St tube goes out.

Post a New Response

(1381286)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by randyo on Thu Jan 14 18:44:37 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by #5 - Dyre Ave on Thu Jan 14 10:44:38 2016.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
While an occasional short turn operating may be acceptable, a semi long term operation as would happen when the N 7 St tubes are out would not be.

Post a New Response

(1381302)

view threaded

Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy

Posted by Steve B-8AVEXP on Thu Jan 14 22:09:11 2016, in response to Re: Upcoming major rehab project on the (L) 14 St-Canarsie Tube, due to Sandy, posted by Stef on Mon Jan 5 07:17:44 2015.

edf40wrjww2msgDetail:detailStr
fiogf49gjkf0d
To 2nd Ave., perhaps?