Re: South Ferry (1) Train Station Fix Could Take Up To 3 YEARS!!! (1199602) | |||
Home > SubChat | |||
[ Read Responses | Post a New Response | Return to the Index ] |
|
Re: South Ferry (1) Train Station Fix Could Take Up To 3 YEARS!!! |
|
Posted by grand concourse on Sun Jan 20 11:55:22 2013, in response to Re: South Ferry (1) Train Station Fix Could Take Up To 3 YEARS!!!, posted by #5 - Dyre Ave on Sat Jan 19 17:35:44 2013. Fingers crossed the next storm that hits won't cause a major rehab job to fix it up again. At some point enough is enough and the feds can't keep plunking down $300 mil + for one location.Now it seems the feds are only picking up 75-90% of the costs. So it will cost the MTA from $50-125 mil. |